  • Sheathing Specification
Sheathing Specification
Objective: The most important of the measures to be taken to ensure energy efficiency in buildings, the number of layers of heat resistant exterior structure is to the desired level. That the structure needs to be done is to apply for external thermal insulation system. The purpose of the insulation system, the structure by jacketed, high or low is to prevent heat from entering the outside and the interior maintain the desired temperature. Coating system can be applied as between two walls or sandwich inside and outside the system can be applied only yield enough of the system in this way can not be obtained.

ARTICLE -1 COATING APPLICATION BEFORE THE MATTERS TO BE CONSIDERED

11th. Especially during renovations glass, wood, care must be taken to avoid damage to the existing structure of aluminum and other elements.

12. Exterior insulation to be applied to damp surfaces should be, flooring and plaster should be dry.

1.3. Exterior sheathing building moisture must be avoided will apply.

1.4. Extension at the front, apparatus, clamps should be dismantled and moved on to set up the system. Pipe and cable should be above the system. Rain gutters should be applied outside the topcoat system and insulation applications must be completed before you start.

1.5. The pier use should be appropriate to the length of the system thickness of scaffolding clamps should be sufficient gap distance between the wall and scaffolding terms of worker safety and the drilled holes for scaffolding clamps (to be upward curve) leaking water should be avoided.

1.6. Regular application for the system to direct sunlight and protected against rain and strong winds. Smooth implementation and elements of comfortable working environment içindış provide thermal insulation system must be stored properly. During the study period adhesives, surface and final coat of plaster in dry and cool conditions, between + 5 ° C should be careful to be stored between + 30 ° C; profile, mesh and so on. system components must be maintained so as not to be deformed and especially off the top of the thermal insulation board, care must be taken to be stored wet.

1.7. The new building was completed interior plastering and painting the walls must be dry so that no moisture accumulation. Failure to comply with these criteria, the reason for insufficient drying times range from the plate with dowels or in shifts and livable.

1.8. The exterior of the sun, using scaffolding network is recommended to protect it from rain and wind.

1.9. Thermal insulation boards can be laid only after the entire surface is covered properly and you have the necessary connections are made resistant to heavy rain.

ARTICLE - 2 APPLICATION MATERIALS TO BE USED (PACKAGE SYSTEM)

2.1. Thermal Insulation Board: the required thickness on all fronts, appropriate intensity, the fire resistance B1 (hard flammable) within the class, maximum 0,040 W / mK with a thermal conductivity coefficient TS 7316 TS certified according to EN 13163 standard, ekspanded (expanded) polystyrene thermal insulation panels will be used . Only doors, window frames according to the thickness of the inner core heat insulation boards can be used.

2.2. Adhesive: the bonding of thermal insulation boards concrete, plaster, brick, concrete, gas. in mineral surfaces and stone wool, used for bonding of thermal insulation boards such as polystyrene, Is the polystyrene surface. 0.1 N / mm² with adhesion, TSE TSEK certificate or cement based adhesives will be used for thermal insulation.

2.3. Reinforced Mortar: the reinforcement mesh coated with the thermal insulation boards, fiber reinforced, high water vapor permeability (sd <0.2 m) Is the polystyrene surface. 0.1 N / mm² with adhesion, TSE TSEK certificate or cementitious grout will be used for thermal insulation.

2.4. Reinforcement Mesh: meet insulation plaster and stresses that may occur in order to prevent cracking min. 160 gr / m² weight 4x4 mm mesh spacing, min. 1500 N / 5cm tensile strength woven fiber mesh with alkali resistant glass fiber will be used.

2.5. Anchors: have not recycled to mount the mechanical application Thermal insulation panels surface, polyamide-based, min. 0.20 kN tensile strength with a large head (6 cm), according to the surface studded with special insulating plastic or insulated steel anchors will be used.

2.6. Corner profiles: corner of the building's structural and aesthetic façade elements in the doors and windows with aluminum centers or self-mesh PVC corner profiles will be used. Exiting the bottom of and necessary points to ensure the removal of other structural surfaces of the drip edge profiles rain and water currents will be used.

2.7.So Floor Decorative Siding: Reinforcement plaster on, in order to protect the system against external influences and aesthetics;

a) Cement-based, fiber-reinforced, water-repellent, mineral coating that can be painted over

b) silicon, doped fibers, acrylic-based, self-colored, ready to use silicone coating will be used.

2.8. Top Coat Exterior Paint: Mineral-based silicone emulsion coating to color, high vapor permeability and water repellency, silicone exterior paint will be used.

ARTICLE - 3 PREPARING THE GROUND

3.1. The exterior of the building will be established as well as the profiles of the scaffolding pipe. Applications will be building properly clean the surfaces of the front and be healthy is a prerequisite for an application. Depending on the surface to be cleaned the floor, if available impurities to be removed from the surface, is weak and will be cleared places appropriate spill, reducing adherence, prevent adhesion of dust, sand and be free of all contaminants such as oil, herself unable to move and blistered surface shall be cleaned. The bottom will fall to 2-3 m wide scaffolding material covered and stucco facade, garden waste such as paint pavement will be prevented from contaminating the ground. Site to work in coordination with officials and landscaping will be protected.

3.2. Building rain downspouts and clamps holding them in front will be removed. If all drainpipes and clamps in exchange for compensation if requested by the apartment management will be refreshed. PVC rainwater downspouts will be used in accordance with TSE standards with a product known in the market (Pimaş Euphrates and so on. As brands) will be replaced by proofing approval.

3.3. The building exterior concrete slabs, columns, beams or parapet wall which occurred cracks in the part to be opened mechanically, existing corrosion damage of reinforcing steel will be eliminated, corrosion inhibitors suitable materials to be used, older (including stucco and concrete disorders) thin or coarse repair mortars repair and will be reinforced.

3.4. Marble walls and window openings in connection with plaster repair will be made.

3.5. Antenna on the building's exterior, air conditioning, window railings and so on. the dismantling of the apparatus and apartment management is the responsibility of the business of assembling into place again.

ARTICLE - 4 THERMAL INSULATION (heat insulation -EPS / XPS) MANUFACTURING DETAIL

4.1. In practice, which starts above the ground level, the first building of the square, plumb and level of application will be studied by the nature of the position and efforts will be launched at the same level level. The application surface should be smooth, plastered surfaces, horizontal and vertical offset of 1 cm on the wall 's exceeds, pinpoint application will be made. Otherwise, surface curvature will break the plane of the board. Before starting the application surface dust, oil and paint residues or cleaned.

4.2. The preferred system 25 kg bag 6 with adhesive in a clean bucket of 8 liters. between the clean and cold water slowly drained. Meanwhile, a low speed drill to help with this mixture for 5-10 min. mixed. After re-mixed mortar to rest for 1-2 minutes with a low speed drill. The useful life of the mortar is between 1.5-2 hours. After this period of time remaining mortar should not be used in any way.

4.3. Back to put insulation adhesive insulation boards, 5 cm wide each side of the plate, in the middle of the strip and a fist-sized pieces 2-3 cm in 2-3 will be applied as a spot heap. The amount of adhesive applied and the height to be adjusted to the floor structure. Appropriate consumption of 4-5 kg / sqm. Care will be taken to complement each other in the corner of the adhesive. 2 According to the weather conditions prepared adhesive should be used within 4 hours. The adhesive applied plate will be mounted on the wall with the help gauge. Plates to the sides of the face to be careful not to get glue and range from having to face, it fails to remain blocked the range to be cut from the same sheet material with the proper thickness range and this will surely be closed.

4.4. After the mortar is ready to paste the desired thickness and the density of the preferred system EPS / XPS insulation plates staggered to the surface, the system must be affixed with adhesive insulation in their future consumption figure of 4-5 kg per square meter. This consumption rate can be increased by an amount in a relatively curved surface. It should never fall below the amount specified in the consumption of adhesive mortar system.

4.5. Curved surface bonding process is done by point bonding method in the ground. Other floors (frame method) slab edges, 5 cm wide middle plate is coated with mortar and mortar is made by placing 3-5 in the size of a fist. Other methods; the notched trowel method is applied to smooth surfaces. The method is applied with a notched trowel adhesive trowel the entire surface of the insulation plate. Either way it should overflow the edges of the insulation plate fees. Placing the insulation plate that must be bottom-up.

4.6. Staggered to place insulation plates and placed gently sliding. The vertical joints between the insulation plate they should not follow each other.

4.7. At least 24 hours after insulation panels attached to the surface of the building should start plugging process. Plugging caused by external factors with the aim of thermal insulation plate to increase the resistance to mechanical stress. Dowel used for this purpose should be headed wide. The dowels to be used and the type of surface it is applied determines the length of the insulation system. Anchors; plastic nail, steel-studded, are divided into varieties such as gas concrete anchors and dowels OSB. If the amount of dowels to be used; The type of anchor determines factors such as the thickness and height of the building's heat insulation plates. Buildings must be increased in the number of edges anchors for building edges are exposed to more mechanical stress.

4.8. Insulation dowel pins will be selected according to a surface. Plugging the process will begin no sooner than after 24 hours after pasting. 24 hours plugging the case can not be expected to be made immediately after the adhesive sheet. To ensure the full strength of the adhesive is required insulation but anchors within 6-24 hours after administration.

49. According to the applied surface type, studded plastic anchors, steel anchors or gas spiked concrete anchors should be preferred. Brick, concrete and brick surface of the type required for anchors will be used. In case of improper dowel type preference can not be obtained sufficient yield from the dowels.

4:10. Anchor heads, to be buried in the thermal insulation boards to bulge in plaster. Drilled holes for dowels capsules should be 45-50 mm from the wall surface and at least 35 mm grip anchors within this hole must be provided. Anchorages, so that the edges and corners of 10-15 cm within the structure will be considered to be mounted.

4:11. The number of anchors should be set in a building facing m² 6. This dowel joints 3 to the confluence of the thermal insulation in the middle of each plate and heat insulation plates should be placed 1. It must be placed in a non-conformity with dowels as possible.

4:12. Plugging corner after the process is finished, window sills and ending locations, or self-meshed aluminum and PVC corner profile will be placed. Purpose of this profile is further confronted with the mechanical factors to increase the resistance of edges and corners and surfaces to achieve the balance.

4:13. After the corner posts are placed on top of the thermal insulation panels on the 1st floor system of cement-based plaster mixed with about 3 kg as the adhesive / m² will be taken with the aid of polystyrene plates with steel trowel on consumption. This plaster dry more than 150 g / m² high alkali resistance reinforcement system in the horizontal and vertical grid ağarlıg 10 cm overlap like giving shares will be placed on the first floor plaster system. The system will be careful to not placing a mesh embedded in plaster on the first floor. Second floor plaster reinforcement system on the net about 2 kg / m² will be pulled to the surface by consumption. Total consumption will be 5 kg per square meter stucco.

4:14. After sufficient drying time façade will be covered with fine grain mineral textured coating systems.

4:15. After allowing sufficient drying time for the coating formed mineral will switch to painting.

4.16. After driven over mineral plasters for decorative purposes and system protection of the system in the desired color silicone exterior paint will be applied 2 coats. (Consumption 350-380 gr / m²).

Article - 5 OTHER ISSUES

5.1. The first quality products, all the products the company will be used and will never use second quality product in case of detection material will be removed from the immediate work area. If TSE products can be delivered to the authorities if requested.

5.2. Business area covered by the employer for the transferred inventory and supplies, adequate size and a locked door will be allocated space.

5.3. Electricity and water needs with the needs of the Contractor shall be borne by the employer free of charge.